2024 May formal enforcements

Penalty Notice issued to Sunterra Energy Pty Ltd

(SSD-9254) Mid-Western Regional LGA

On 1 May 2024, NSW Planning issued a Penalty Notice for $15000 to Sunterra Energy Pty Ltd, for failing to comply with conditions of consent for the Wollar Solar Farm development for not implementing the Cultural Heritage Management Plan. The company has since engaged, consulted and worked with the Local Aboriginal Council, implementing feedback from LAC and has updated the Cultural Heritage Management Plan. The company has also delivered additional Aboriginal Cultural Awareness training, in consultation with the Local Aboriginal Land Council, to contractors and subcontractors.